MAY 6 PROGRESS REPORT by Bunny

It was another beautiful day of fine weather and plenty of black flies, as you can see by most of our headgear. At day's end, Maple Grove was looking pretty good. Cabin 1 had 2 walls up with only 2 guys, and cabin 2, with a larger crew, was well underway with 4 walls finished. Cabin 3 was prettied up with an awesome railing and finishing touches.


Up on Oak Ridge, Norm's team had a wall up and the deck half done. As well, construction of cabin 8 began, with the putting up of the floor beams and the joists. Justin wields a mean chainsaw!